Key point. If the contractor failed to start on time or works so slowly that completion by the agreed date is clearly impossible, establish the facts and withdraw. A prediction or missed meeting does not replace proof of progress and remaining work.
Ordinary business work on a movable item; agreed final date; late start or pace makes timely completion clearly impossible; no customer-created obstacle.
Excludes special work/procurement, evidence-free delay predictions, amended deadlines and customer obstruction. No automatic recovery of every advance or claimed loss.