Key point. Where the former obstacle is actually removed, identify proof, operations ready to resume and readiness date. Readiness alone neither changes contractual deadline nor proves actual resumption.
Continuing ordinary business works contract; specified earlier obstacle demonstrably removed and contractor actually ready for identified operations.
Not continuing obstruction, construction, design, consumer works, public procurement, services, ended contract, acceptance or unilateral deadline/price change.